水泥就地冷再生施工要注意什么?
来源:https://www.sddhfjx.com/ 日期:2021-09-22
1、混合料佳含水量现场监测办法,一手抓起一把混合料,用力握实,然后松手让其自由落向地面,正常会立即摔散花,里面没有小团料。反复试验,介于落地松散和抱团之间的临界含水量即最佳含水量,一般比试验单上的最佳含水量数值多1%-2%。
1. The on-site monitoring method of mixture moisture content is to grasp a handful of mixture with one hand, firmly grasp it, and then let it fall freely to the ground. Normally, flowers will be scattered immediately, and there is no small mass in it. After repeated tests, the critical water content between loose and agglomerated on the ground is the best water content, which is generally 1% - 2% more than the best water content value on the test sheet.
2、作业施工水罐车停车时一定要离开已施工或待施工水泥已摊铺路面,以防止漏水引起的局部水大。
2. When the construction water tanker stops, it must leave the paved road of cement that has been constructed or to be constructed, so as to prevent large local water caused by water leakage.
3、施工车辆停放时一定要错开第二天的第一段第一道预工作面,以防止耽误第二天的人工水泥摊铺,施工车辆最好不要停放在已完成施工的路面上。防治破坏新建结构和影响后期洒水养生。
冷再生机出租
3. When parking construction vehicles, the first pre working face of the first section of the next day must be staggered to prevent delaying the artificial cement paving of the next day. It is best not to park construction vehicles on the road surface that has completed construction. Prevent and destroy the new structure and affect the later watering and curing.
4、避免犯“过压”的错误,即过度压实。若达到材料的最大密实度后仍然继续碾压,则会破坏材料,反而降低其密实度。
4. Avoid the mistake of "overpressure", i.e. over compaction. If the rolling is continued after reaching the maximum compactness of the material, the material will be damaged and its compactness will be reduced.
5、冷再生机的施工作业应该在每天下午15:00—16:00之间结束,以便后续施工能在天黑前结束。
5. The construction of cold regenerator shall be completed between 15:00 and 16:00 every afternoon, so that the subsequent construction can be completed before dark.
6、每天冷再生租赁机结束施工进行洗刀停车后,应通知操作手仔细检查车况并更换刀头,以免耽误第二天的施工进度。
6. After the construction of the cold regeneration rental machine is completed and the tool is washed and stopped every day, the operator shall be notified to carefully check the vehicle condition and replace the tool head, so as not to delay the construction progress of the next day.